Hello,
I'm trying to import data from XML exported from MS Project.
Project's tasks ID start from 0, but if task ID is equal to 0 in the JSON file then I got the error "Error: Invalid tasks tree. Cyclic reference has been detected on task 0".
Is this a bug or an expected beheaviour?
Best regards,
Emanuele
The text was updated successfully, but these errors were encountered:
However, in DHTMLX Gantt there is an invisible root task that is a parent of all tasks on the root level.
So, when you add a task with the 0 ID, it is assigned to the invisible root task, and its parent value becomes 0. So, it creates the cyclic tree.
Hello,
I'm trying to import data from XML exported from MS Project.
Project's tasks ID start from 0, but if task ID is equal to 0 in the JSON file then I got the error "Error: Invalid tasks tree. Cyclic reference has been detected on task 0".
Is this a bug or an expected beheaviour?
Best regards,
Emanuele