Contents
The HCA metadata schema defines the shape of metadata documents being exchanged between components of the DCP/2. It therefore constitutes a de-facto contract between those components. The DCP consortium reviews schema changes collectively to ensure that all teams in the consortium approve of a schema change before it
- affects the master branch of the metadata-schema repository,
- is published on schema.humancellatlas.org, or
- is used by metadata staged for import into the production instance of TDR
Changes to the HCA metadata schema, including seemingly minor ones, can have significant impact on the individual components of the DCP system. Even the addition of a property can, in some case, require significant work in metadata consumers like the Data Browser, especially if those consumers are required to interpret the added property. It would be difficult to explicitly define the criteria for classifing schema changes by impact. Instead, the impact is determined individually for every schema change. Changes that are deemed of low impact are fast-tracked through a lighter-weight review process.
A schema change is a carefully selected set of related modifications to one or more of the JSONSchema documents in the metadata-schema repository. If a schema change can be made smaller by excluding a particular change to a schema document without sacrificing the desired end-user value, it should be made smaller, so as to not overwhelm the reviewers with a mix of orthogonal concerns.
On the other hand, the set of changes shoudn't be too small either: all schema document changes that are necessary to achieve the desired end-user value should be combined in one schema change. If certain end user value is achieved in a series of many small schema changes, reviewers will likely not be able to see the big picture until they review the changes at the end of that series, at which point it may be too late to reverse course.
Some schema changes warrant an update to the DCP/2 System Design specification. Whether they do or not is established collectively and early on during the review process.
Schema changes are often motivated by the need to capture novel information about the experimental design, phenotypes or sample collection process as submitted by a participating laboratory, in a form that the current schema is not able to sufficiently capture. Participating labs often don't have the resources or tolerance for a prolonged submission process and are likely to walk away if it takes too long to incorporate their submission into the DCP/2.
The DCP/2 therefore needs to balance the celerity with which it adopts schema changes on one hand against the effort needed to make all components compatible with those changes on the other. The earlier a proposed change faces scrutiny by the entire DCP/2 consortium, the better will the consortium be able to negotiate the right balance, simply because the change will not yet have permeated through the system, making it easier to make adujustments to the proposed schema changes.
Any member of the consortium can sponsor a schema change. The sponsor can delegate authorship of the corresponding PRs to other members of the DCP/2 consortium. While the PRs that comprise a particular schema change don't all need to have the same author, the sponsor must ensure that all those PRs are semantically consistent with each other.
The process of reviewing schema changes utilizes Github's pull request (PR) feature. Every schema change review begins with a PR against the staging branch of the metadata-schema repository. The develop and integration branches of that repository are not used anymore. Reviewers first determine
- the overall impact of the change
- whether the schema change is sized correctly
- whether the change requires updating the specification in the dcp2 repository
- whether it requires updating the test metadata in the schema-test-data repository for other components to code unit tests against
If a change requires specification changes, the metadata-schema PR review is suspended and a PR is filed against the dcp2 repository and reviewed there. Once that PR is approved, the metadata-schema PR is revised to match the approved specification after which it is reviewed again.
Schema changes that are sized correctly and have negligible impact to other components, are considered adopted by the DCP/2 as soon as the PR against the metadata-schema repository is approved. No further reviews of PRs against other branches or repositories are required.
Schema changes that are sized correctly, and that are of some impact to other components, may require more involved testing. There are two ways of testing schema changes:
- (Meta)data exhibiting the proposed schema changes are first staged and then
imported into the dev instance of TDR after which downstream components
use the resulting dev snapshot to test the code changes that are required
to support the schema change. The Ingest component can only populate
staging areas from its staging instance, so the metadata-schema PR must
first be approved provisionally [1], merged and deployed to
the
staging
deployment of the Ingest component. - (Meta)data exhibiting the proposed schema changes are committed to a feature
branch of the schema-test-data repository, and a PR is filed for that
branch. The schema-test-data repository can only populated using the
staging instance of the Ingest component, so the metadata-schema PR must
first be approved provisionally [1], merged and deployed to
the
staging
deployment of the Ingest component.
[1] | (1, 2) the provision being that the schema change may need to be amended in a follow-up PR |
The reviewers of a PR can request either testing strategy.
In some cases a lab submission not only involves a schema change but also introduces a novel way of linking the metadata enties into subgraphs. In those cases, reviewers are likely to request testing strategy B. A request for either strategy should be reasonably motivated. Possible reasons include
- the need to not only review schema changes but also review how those changes affect actual metadata documents
- the need to test future, unrelated code changes against the test metadata, so as to make sure that those future changes don't introduce regressions. Especially graph changes fall into that category.
Schema changes that are sized incorrectly need to be revised.
Pull requests against the dcp2, the metadata-schema or the schema-test-data repositories are reviewed and approved in exactly the same way, provided they are involved in a semantic change to either the DCP/2 specification, a DCP/2 standard operating procedure or a metadata schema change:
As a PR author
Announce the PR on the
#dcp2
channel on Slack, @-mentioning all Designated reviewers. If the changes in the PR match the criteria for expedited review, label the PR asexpedited
in GitHub and note that fact in the Slack announcement thread.In GitHub, request a review from all Designated reviewers.
Wait one week. For expedited review, wait two business days. A business day is a weekday that is not a holiday for any of the participating institutions.
If this is the first cycle of a normal, non-expedited review, remind about the PR on the
#dcp2
channel on Slack, @-mentioning requested reviewers that haven't yet reviewed the PR.If either
- all reviewers approve of the PR without conditions or
- two weeks (or two business days, for expedited review) have passed since step 1 and there are no binding reviews requesting changes,
merge the PR. You are done unless any of the approvals are conditional. A conditional approval is one that's dependent on successful testing using one of the strategies mentioned in Review process overview. The condition has to be specified in the summary comment on approval. If testing fails, a reviewer may request amendmends to your changes. These requests are made as comments to the original, now merged PR. Open another PR with the requested amendmends and start at step 1.
If a reviewer requests that you first update the DCP/2 system design specifcation or standard operating procedures first, suspend work on this PR and open another PR against the dcp2 repository. Start at step 1 there. Once that PR has been approved, update this PR branch with any follow-up changes resulting from the dcp2 PR review process and resume this PR at step 1.
If a reviewer requests that the PR be changed from expedited review to normal review, remove the label and note that fact on the Slack announcement thread. The current and subsequent review cycles revert back to the normal timeline.
Otherwise, respond to every review comment either by making a source code change that you think appropriately addresses the comment or by replying with a comment explaining your opposition to the change or asking for more information. When addressing a set of related review comments with a source code change, try to commit that change separately from those addressing other related sets of review comments. Avoid constantly squashing the PR branch unless doing so helps reviewers to better understand the branch history.
Start another cycle by requesting a review from the reviewers currently on the PR, even those that already approved the PR or just commented on it. Proceed to step 3.
Steps 1, 2 and 9 must be done on a weekday.
As a PR reviewer
- Respond to review requests within one week of the request (two business days for expedited review) or
- Name a delegate within one business day of the request. Do so by cancelling the request for review by you and requesting a review from the delegate instead. Make a normal (non-review) comment on the PR, announcing the delegation.
- Review the PR in good faith. Ask specific questions or make specific suggestions. If you can't find anything objectionable in the PR, approve the PR as soon as possible. Don't get lost in details.
- If you accept the PR author's response to a comment made by the reviewer, mark the comment thread as resolved on Github.
Once a designated reviewer delegated the review, none of the designated reviewer's comments or reviews are binding. It's acceptable to direct the delegate but that should be kept to a minimum and ideally be done outside of Github e.g., Slack or E-Mail.
A delegate reviewer can only delegate back to the designated reviewer that named them, and only after the PR author rerequested a review from the delegate.
Only comments and reviews by mediators, designated reviewers or their delegate are binding. Other reviews should be dismissed by the author. Other comments can be ignored.
Reviews by designated reviewers or their delegate can be dismissed by the Mediators.
At no time during the life-time of the PR can there be more reviewers listed on the PR than there are entries in the lists of Designated reviewers and Mediators.
Certain trivial changes are eligible for a compressed review timeline, as defined in Pull request reviews above. The following changes are eligible for expedited review:
- Additions of enum values to
project.hca_bionetworks.hca_tissue_atlas
Review comments and replies by authors should be kept brief. Typically, review comments made during a review cycle are addressed by the author and marked resolved by the reviewer during the next cycle. Any disagreement that cannot be resolved in two cycles should be discussed in a conference call to which the the PR author invites the Mediators and all reviewers currently on the PR.
- Enrique aka
@ESapenaVentura
(EBI) - Amnon aka
@amnonkhen
(EBI) - Nate aka
@ncalvanese1
(Broad) - Hannes aka
@hannes-ucsc
(UCSC) - Dave aka
@NoopDog
(UCSC)
- Kathleen (Broad)