Back End team's contributions to the Project Plan #303
Replies: 5 comments 2 replies
-
Define API Conventions
First 1 week of back-end work.... |
Beta Was this translation helpful? Give feedback.
-
Write a database manipulation codebase
The starting task can be finished first week. (Together with conventions task) |
Beta Was this translation helpful? Give feedback.
-
Back-end code for Milestone 1This should be a decision of all teams for sure.
2 weeks (after conventions and database manipulation codebase tasks are finished) will be ok I think. |
Beta Was this translation helpful? Give feedback.
-
Final Milestone suggestions |
Beta Was this translation helpful? Give feedback.
-
İyi düşün Back-end team: Automated testing:-)
|
Beta Was this translation helpful? Give feedback.
-
It will be a good practice if we reply to comments about different ideas one by one.
Beta Was this translation helpful? Give feedback.
All reactions