BCF 3.0 Implementation and Integration Plan

  1. Keep meeting weekly
  2. Schedule a BCF 3.0 Launch Hackathon on the 17th and 18th of Feb 2021
  3. Create a slack channel for BCF 3.0 integration - everyone should communicate openly there so that we have cross-team awareness

BCF 3.0 Implementation tracking

Vendor Server/Client Status ETA
Solibri Client XML is well progressed, API implementation in progress ~ Mid Feb 2021
Oracle Aconex Server Both BCF API and BCF XML in a good state ~ End of Jan 2021
Catenda Server Initial BCF API 3.0 implemented; Started on BCF-XML ~ Feb 2021
DDS Client Not started, recently improved the end-to-end testing with servers ~ Jan 2021 for internal testing
Graphisoft Client Not started, currently supporting XML only, would like to have more features, such as pins Unknown
xBIM and the Revit Plugin (by M.C) Client Not started ETA Jan 2021 for XML, unknown for API
KUBUS / BIMcollab Server & Client Not started, ETA for start unknown Unknown
ALLPLAN BIMplus Server TBA unknown
Asite Server Implementing No ETA
Trimble Server Progressing BCF 2.1 support No ETA