Date and Time: 28th July'23
1. Executive Summary: This SITREP contains the current progress of Skill Tree, both frontend and backend.
2. Current Situation - Frontend: The design work is going on (In Progress), the development of the other screens has been started as mentioned by @vaibhav
3. Current Situation - Backend: The API contracts and entities are decided, the work for writing the test cases have been started by Vikhyat, and database side of things are done by Bhavika.
4. Challenges The time taken for review of API contracts / Entities was slightly higher due to unavailability of the team members
5. Next steps The primary focus is to get the database setup done and test cases setup done, so the thing which will be left is the APIs implementation