- Click on "Override Project Default values" in the top right corner of the 'Project Overview' page.
-
It will take you to a form showing the fields that were default which you can change. You can change these two fields to reflect the values for this particular project.
-
Once you have edited these fields, click on the blue button that says "save".
The pre-defined default values set at the organisational level will now be overridden for this project, replaced by the new values you have set.